How long should it take to pour a 10 ft. by 10 ft. concrete slab? | Less than 2 hours | 52% | 2-4 hours | 23% | 4-6 hours | 4% | More than 8 hours | 4% | Not sure | 14% | | | Question: How long should it take to pour a 10 ft. by 10 ft. concrete slab? Top Answer (52% of 21 votes): Less than 2 hours.
Answer: More than 8 hours Explanation: Pouring a 10 ft. by 10 ft. concrete slab involves several steps that collectively determine the total time required. Here’s a general breakdown of the process and the time involved:
1. Site Preparation: This includes excavation, leveling, and preparing the subgrade. Depending on the condition of the site, this can take a few hours to half a day.
2. Formwork Installation: Setting up the formwork to define the perimeter of the slab. This can take a couple of hours, depending on the complexity and size of the slab.
3. Rebar Installation (if applicable): If reinforcement is needed, installing rebar within the formwork. This step can take additional time, typically a couple of hours.
4. Concrete Delivery: The time for concrete delivery depends on factors like distance from the batch plant, traffic conditions, and logistics. Typically, this can range from 30 minutes to 1 hour.
5 Pouring and Leveling: Pouring the concrete into the formwork and leveling it using tools such as screeds and floats. For a 10 ft. by 10 ft. slab, pouring and initial leveling can take about 1 to 2 hours.
6. Finishing: Smoothing and finishing the concrete surface to achieve the desired texture and appearance. This step can take another 1 to 2 hours.
7. Curing: Allowing the concrete to cure and gain strength. Initial curing typically requires at least 24 to 48 hours of protection from drying out too quickly, depending on weather conditions.
Total Time Estimate:
Preparation: 1 to 4 hours (depending on site conditions)
Formwork and Rebar: 2 to 4 hours
Concrete Delivery and Pouring: 1 to 2 hours
Finishing: 1 to 2 hours
Curing: 1 to 2 days (for initial curing)
Overall Duration:** From start to finish, pouring and completing a 10 ft. by 10 ft. concrete slab typically takes approximately 1 to 2 days. However, factors such as weather conditions, site accessibility, and complexity can affect the actual time required. It's advisable to plan accordingly and coordinate with your c | Midtex Services | Answer: Less than 2 hours Explanation: It should take 10 minutes to pour 1 yard of concrete | Solid Solutions Concrete LLC | Answer: Less than 2 hours Explanation: Yes | Capristo concrete | | ProMatcher | Answer: Not sure Explanation: Depends if you are talking about excavation, forming and finishing. | Elite Concepts | Answer: Less than 2 hours Explanation: Pouring should take 30 minutes if truck can reach area. | Allied Concrete LLC | Answer: 2-4 hours Explanation: The placement period of the pour would be relatively short, depending on accessibility, and crew ability, but the set time would be 2-4 hours from placement influenced some by weather, regardless of the size of the placement. | Maven Group LLC | | ProMatcher | Answer: Not sure Explanation: Depends on forming and if you can get truck to are or have to use wheelbarrow | DIRTCO CONSTRUCTION |
|